Reports of town officers of the town of Attleborough 1936, Part 14

Author: Attleboro (Mass.)
Publication date: 1936
Publisher: The City
Number of Pages: 212


USA > Massachusetts > Bristol County > Attleboro > Reports of town officers of the town of Attleborough 1936 > Part 14


Note: The text from this book was generated using artificial intelligence so there may be some errors. The full pages can be found on Archive.org (link on the Part 1 page).


Part 1 | Part 2 | Part 3 | Part 4 | Part 5 | Part 6 | Part 7 | Part 8 | Part 9 | Part 10 | Part 11 | Part 12 | Part 13 | Part 14 | Part 15


When the wells had been constructed to the point where only the con- struction of the well houses and installation of the pumps were necessary, another pumping test was begun. These tests were run for several days during which time the effects upon all test wells were noted. Again the State Department of Health approved them for final construction, installation and testing.


The final construction of the well houses and installation of the pumping machinery were completed in the late fall whereupon the final tests were run with both wells operating simultaneously under direction of the State. The test was run from December 8 to December 24, 1936, after which final approval of the two wells was given by the Massachusetts Department of Public Health with the understanding that the entire water supply pumped at the South Attle- boro plant be treated. As mentioned before, this treatment had been recom- mended for several years by the State Department.


Final construction of the supply line from the wells to the pumping station had been rushed to completion before the final tests were begun.


When the satisfactory supply from these wells became apparent in the fall of the year studies were immediately begun for the construction of a treat- ment plant. On December 2, 1936, the contract for the construction of the water treatment plant was signed by the contracting firm of James A. Munroe & Sons; the sub-contractor for installation of the treatment equipment was the Norwood Fngineering Company of Florence, Massachusetts. The construction was actually begun before the end of the year; consequently the City will have at its disposal within a short time an additional water supply estimated at 1,200,- 000 gallons per day on the basis of continuous operation.


The additional supply which the new development makes possible insures the City of an adequate supply of water for emergency use and through the dry summer periods.


The importance of a good supply of water for the community is so vital that every citizen should take an active interest in obtaining for the community a water distribution system of modern equipment and maximum value to the public.


SEWER DEPARTMENT


During the year the entire filtering area was cleaned as usual. However, the present area is not sufficient to properly filter and dispose the quantity of sewage which at present must be taken care of. Following are figures showing the actual amount of sewage being filtered by the present area and figures which, according to best authorities on sewerage practice, show what our filtering area should be for proper disposa of present quantity:


184


ANNUAL REPORT


Present area of filter beds 15.5 acres Daily average of sewage for 1936. 1,074,954 gallons Present amount of sewage per acre per day. 63,350 gallons Recommended amount of sewage per acre per day according to authorities on American sewerage practice. 27,000 gallons


Using the daily average amount of sewage for 1936 together with the above recommended amount of sewage per acre per day, the necessary filtering area for our sewage disposal plant would be 39.8 acres.


Using the maximum amount of sewage for any one day in 1936 which was 5,018,900 gallons, together with the recommended amount of sewage per acre per day, the necessary filtering area for this maximum would be 185.9 acres.


Using the area required for the daily average amount of sewage for 1936 according to the recommendations of authorities on this subject, which we found to be 39.8 acres, it is found that our present filter area is only 39% of the area required for adequate disposal of the sewage.


In view of the above facts I would recommend an early study be made for adequate facilities of our sewerage disposal system.


Very little flushing of sewer mains could be done during the year due to the inadequate funds allotted. I would therefore recommend that a larger appropria- tion be made in the future to avert serious conditions.


Along the railroad in Hebronville, just south of Knight Avenue, there is approximately 500 feet of elevated 30-inch trunk line sewer constructed of re- inforced concrete on concrete piers. This line has been the cause of considerable trouble due to the leaking of sewage at the expansion joints; also considerable spalling of the concrete has taken place. During the fall the worst leak was temporarily repaired at considerable expense.


Studies have been underway for some time relative to the replacement of this structure with a 30-inch iron pipe. This type of pipe would have pro- visions for expansion at the joint couplings, and the material would be of a com- position to withstand the action of the acids inherent in sewage. I recommend that immediate consideration be given the project prior to any serious break which would be more costly and detrimental to health conditions.


SEWERS, OPERATION AND MAINTENANCE


Caretaker at Beds


$1,359.42 .


Maintenance and Improvement of Beds


Labor $191.16


Material


241.64 432.80


Insurance


96.35


Taxes


Town of Seekonk. 67.50


City of Pawtucket.


14.36


81.86


Maintenance and Operation of Sewer System


Labor. $147.89


City of Attleboro-


Water Charge. 100.00


Material


4.81


252.70 $2,223.13


185


ANNUAL REPORT


SEWER CONNECTIONS


Total connections January 1, 1936 1861


Buildings served. 2073


Connections added during 1936. . . 10


10


1871


2083


SPECIAL ACCOUNTS North Main Street and Commonwealth Avenue Widening


In July North Main Street from Holden Street to Commonwealth Avenue was treated with a bituminous material and covered with sand. There were also other miscellaneous items for labor and material charged to this account.


Labor


$ 141.06 844.02 $ 985.08 Material


Emory and Pine Street Improvement


There were miscellaneous items in connection with maintenance charged to this account.


Labor $ 7.98 101.37 $ 103.35


Material


Adamsdale Avenue Reconstruction


In June Adamsdale Avenue from Allen Avenue to Brown Street was given a surface treatment of bituminous material and sand; other miscellaneous items complete the expenditures shown.


Labor Material


$. 13.03 312.96 $ 325.99


Leroy Street Improvement


The expenditure as shown is a maintenance cost.


Material


$


50.00


Improvement of Mechanic Street E. R. A.


The expenditures as shown are maintenance costs. Labor Material


$ 40.63 327.47 $ 368.10


Equipment Repairs


The expenditures as shown are for maintenance costs.


Labor Material


2.28 8.86 $ 11.14


186


ANNUAL REPORT


Improvement of Pond Street E. R. A.


In May the entire length of Pond Street was treated with a bituminous material and sand; also the guard fence was repaired plus other miscellaneous items.


Labor


Material


$ 59.20 237.73 $ 296.93


Pond Street E. R. A. Drain


The expenditures as shown are for miscellaneous items of maintenance.


Labor $ 5.00 56.12 $ . 61.12 Material


1


South Attleboro Rail Elimination and Replacement


The work done under this account includes such items as building a stone wall at Wilbur's, repairing stone wall at Balser's, relocating fence, removing trees, grading lawn at Wightman's due to sidewalk relocation and other incidental work.


Labor


$ 292.59 576.34 $ 868.93 Material


West Street Construction


Under this account is the construction of a stone wall on West Street along the McCormick property. The wall is 226 feet long and in volume is 95 cubic yards. The work consisted of considerable excavation, tree removal and grading of sidewalks; also repair of granolithic walk, the placement of approximately 60 feet of granite curbing around the corner at North Main Street, and regrading lawns and driveways due to construction damages, plus miscellaneous items.


It was necessary to construct the wall at McCormick's on West Street after the repaving of the street in order to provide a sidewalk on this side of the street. There was an existing high bank which had to be cut down to grade, and the retaining wall was then constructed for protection to the public and the property.


Labor Material


$ 1,034.27 877.62 $ 1,911.89


Ashton Road Construction


In May the entire length of Ashton Road was treated with a bituminous material and sand. There are also other miscellaneous maintenance items included.


Labor. $ 7.40 223.28 230.68 Material


.


187


ANNUAL REPORT


Hebronville Guard Fence


Work done under this account includes setting up new and repairing guard fence in Hebronville along South Main Street.


Labor $ 49.66 35.42 $ 85.08 Material


North Avenue E. R. A. Drainage


An extension to the culvert at Deantown Road was built and a headwall for same constructed; also the grading and inlet stone reset on one of the catch basins. All basins and pipe lines were cleaned.


Labor


$ 39.27 48.70 $ 87.97


Material


1925-1927 Street Widening Loan


Various expenditures for maintenance are included under this account.


Labor


$ 19.81 463.72 $ 483.53 Material


Construction of Ruggles Street E. R. A.


The entire length of Ruggles Street was treated with a bituminous material and sand. There were also other miscellaneous items including sidewalk grading and excavation.


Labor Material.


50.41 99.59 $ 150.00


Curbing and Cement Walk Construction


Granolithic slabs for sidewalk replacement on Peck Street were constructed and placed.


Labor Material


$ 44.84 9.09 $ 53.93


Construction of Central Street E. R. A.


In May Central Street was given a surface treatment of bituminous material and sand on the entire length of the street.


Labor. Material


$ 4.63 95.37 $ 100.00


188


ANNUAL REPORT


East Fourth Street Improvement E. R. A.


Under a Federal project the above street was reconstructed from County Street to the Ten Mile River. The work included the reconstruction and placing of a gravel and bituminous surface, paving of gutters, construction of gravel sidewalk and miscellaneous items in connection with construction.


Labor Material


$ 113.16 442.14 $ 555.30


North Main Street Construction E. R. A.


Under a Federal project North Main Street was reconstructed from Sanford Street to Elizabeth Street. The work included the placement of a 7-inch stone penetration pavement, resetting of curb, removing trees, replacing granolithic walks, resetting manholes and other miscellaneous work pertaining to the con- struction. The rail removal was taken care of by the Interstate Transit Corpora- tion.


Labor $ 1,514.70 Material 5,431.95 $ 6,946.65


Construction of Bliss Avenue E. R. A.


In May the entire length of Bliss Avenue was given a surface treatment of bituminous material and sand. The sidewalks were also gravelled and graded. Labor $ 23.77 153.13 $ 176.90 Material


Sidewalk Curbing for Capron Park, Horton Field and South Attleboro School


Expenditure as shown is for miscellaneous charges. $ 12.29 $ 12.29 Material


County Street Drainage and Construction E. R. A.


Under a Federal project drainage line construction from Sixth Street southerly was completed during the year. The work consisted of excavation of trenches, laying pipe, refilling trenches, construction of catch basins and manholes, also incidental work to the general construction. This work was completed in preparation for the pavement construction which followed later.


Labor Material


$ 498.47 686.77 $ 1,185.24


1935 South Main Street Hebronville Drainage E. R. A.


Under a Federal project drainage construction from the Attleboro-Seekonk line northerly to the river bridge was undertaken prior to the opening of the road construction project. The work consisted of excavating trenches, laving pipe, refilling trenches, constructing catch basins, manholes and other miscellan- ยท eous work incidental to construction.


189


ANNUAL REPORT


Labor


Material


$ 137.56 1,048.59 $ 1,186.15


South Main Street Improvement


Under a Federal project the part of the roadway occupied by street railway tracks was reconstructed from a point at Atwell's curve to the Attleboro-Seekonk line. The work included the gravel refill and placement of a 7-inch stone penetra- tion pavement, except for a distance of approximately 1200 feet which was a 2-inch cold mix; also paving a stone gutter and curb the entire distance, setting circle curb, gravel filling and grading and sidewalk the entire distance on one side of the street, setting new fence and other work incidental to the general con- struction.


Labor. $ 1850.24 Material $ 5,558.02 $ 7,408.26


Dexter Street Construction


Under a Federal project Dexter Street from South Main Street 2200 feet easterly was reconstructed and a gravel roadway with a bituminous surface placed the entire length. The work included excavation, gravel refill, bituminous surface, relaying 200 feet of water main, constructing additional sidewalk area to concrete bridge, constructing and grading gravel sidewalks, paving gutters, placing guard rail on bridge, and other work incidental to the general construction.


Labor $ 945.96 1,195.93 $ 2,141.89 Material


County Street Pavement Construction


This account covered generally the entire reconstruction of County Street from North Main Street to County Square. The work consisted of excavation, gravel refill, placing a 7-inch stone penetration pavement, resetting curb, placing new circle curb, paving, resetting manholes, placing sidewalks, constructing and grading gravel sidewalks, and also other work incidental to the general construction.


Labor Material


$ 4,557.43 9,368.54 $13,925.97


Public Works Highways-Chapter 464-Acts of 1935


County Street-Third to Olive Street: This account was set up through an allotment from the State of Massachusetts in accordance with Chapter 464, Acts of 1935. An application was sent to the State Department of Public Works to have $4,052.00 of the allotment set aside for purchase of materials for the County Street reconstruction project between Olive Street and Thirteenth Street. Their approval was subsequently given. Accordingly, the amount was used for purchase of materials for the construction which is outlined in the preceding account.


Material.


$ 4,052.00


190


ANNUAL REPORT


Public Works Highways-Chapter 464-Acts of 1935


County Street-Olive Street to Thirteenth Street: This account was set up in a manner identical to the preceding account, except that the application was made for the balance of the total allotment which amounted to $2,777.61 to be spent on County Street from Olive Street to Thirteenth Street and approval was obtained. Accordingly, the amount was spent for materials in the location stated for the reconstruction of County Street as described in a preceding account.


Material


$ 2,777.61


Tanager Road Construction


In May Tanager Road from North Main Street to Bank Street was recon- structed. The work included excavation, gravel refill, placement of a bituminous surface, construction and grading of gravel sidewalks and other work incidental to the construction.


Labor.


ef 234.79 516.33 $ 751.12 Material


South Avenue Reconstruction


This account is for the reconstruction of South Avenue from Thacher Street to Uhlig's Hill, the construction being under the Chapter 90 regulations in which the State, County and Municipality share the cost. The contract for the construction was awarded to the John Deveney Company.


The reconstruction includes extensive drainage work plus the placement of a 7-inch stone penetration road. Up to the end of the year considerable progress has been made in placing the drainage system for surface and sub-grade drainage. The work will be continued to completion in 1937. Following are the expenditures to the end of 1936.


Labor. Material


$ 142.86 9,570.58 $ 9,713.44


Pembroke Avenue Construction


In May construction of Pembroke Avenue was begun from County Street to Hawthorne Street. The work was completed in September and included excavation, gravel refill, placing bituminous surface, constructing and grading gravel sidewalks, and also other work incidental to the general construction.


Labor $ 410.11 407.53 817.64 Material


Fisher Street Construction


In September the work was begun for the construction of a portion of Fisher Street. Up to the end of the year the work has included excavation and gravel refill.


Labor Material


$ 311.28


113.23 424.51


191


ANNUAL REPORT


Fenton Avenue Construction


Under a Federal project Fenton Avenue from Brown Street to Washington Street was reconstructed and approximately 500 feet of 6-inch new water main placed. The work included excavation, gravel refill, placement of bituminous surface, construction of gravel sidewalks, relaying approximately 375 feet of 6-inch water main and other work incidental to the general construction.


Labor $ 486.74 615.21 $ 1,101.95 Material


Brook Street Drain Project


Under a Federal project work was begun in December on Brook Street at Thacher Brook to construct a pipe line 33 inches in diameter, running along Brook Street to Falmouth Street; then along Falmouth Street to Thacher Brook. This will eliminate the open brook which previously cut across lots from the Falmouth Street end to the Brook Street end. Up to the end of the year good progress had been made on the excavation of the trench which will require sheeting and pumping. This project will be completed in 1937.


Labor


$ 92.19 928.94 $ 1,021.13 Material


Newport Avenue Water Main


The charge shown is a small maintenance item.


Labor


$ 1.88


Fenton Avenue Water Main Line Replacement (W. P. A.)


Under a Federal aid project an old two-inch water main was replaced with a six-inch main and other specials necessary to the project.


Labor Material


$ 87.92 524.24 $ 612.16


Pembroke Avenue Water Main Replacement


In conjunction with the general improvement of Pembroke Avenue, an old two-inch main line was replaced with a six-inch line and necessary specials. Labor Material


406.90 807.18 $ 1,214.08


Pleasant Avenue Water Main Replacement and Extension (W. P. A.)


Under a Federal aid project work was started on Pleasant Avenue recon- structing the entire length and removing an old two-inch main line and replacing it with a six-inch main line. This project will be completed in 1937.


Labor Material $ 10.85 332.40 $ 343.25


192


ANNUAL REPORT


Prince Street Water Extension


This work was begun in 1936 and calls for i six-inch main line extension from Payson Street southerly. The extension is being placed to accommodate new construction. This project will be completed in 1937.


Labor


Material


21.64 471.05 $ 492.69


EXPENDITURES 1936-PUBLIC WORKS DEPARTMENT Charges to December 31, 1936


General Administration:


Superintendent's Salary


$ 3,534.63


Eng. Salary, Asst. Eng., Rodman, etc.


7,469.11


Clerical Labor.


4,450.99


Engineering Supplies


64.90


Office Supplies.


142.80


Insurance .


44.92


Superintendent's Auto Maintenance.


53.13


Rent.


756.00


Light.


21.80


Telephone


118.46


Incidentals.


4.45


$ 16,661.19


Highway Division :


Resurfacing


1,458.76


Drains


1,732.09


Street Sweeping


790.30


Street Patching


6,004.33


Street Cleaning


1,412.92


Sidewalk Maintenance


442.65


Equipment, maintenance and repair.


651.04


Road Rollers .


226.81


Auto Maintenance


75.12


Road Oil and Tar.


5,383.86


Crushers. .


218.94


Ten Mile River and Thacher Brook


29.42


Insurance .


915.99


Rent, Maynard Street Land.


69.60


Vacations .


425.60


Signs, Clock and Numbers


145.28


Incidentals.


60.32


Snow and Ice


5,405.80


Sidewalks and Curbing


1,114.33


27,051.02


New Equipment.


5,998.39


Street Lighting


29,511.62


Bridges, Fences and Culverts.


487.86


193


ANNUAL REPORT


Water Division:


Maintenance Payroll.


10,288.41


Maintenance Material


897.99 1


New Meters. .


893.08


Services.


1,508.38


Shop and Barn


413.15


Maintenance of Buildings


411.13


Main Line Maintenance.


1,007.07


Auto Operation.


599.45


Insurance


1,072.20


Taxes.


324.51


Incidentals.


2.80


Emergency Thawing.


50.80


Liens


57.78


17,526.75


Main Line Extension


2,649.93


Newport Avenue Water Main


1.88


Fenton Avenue Water Main Line Replacement


612.16


Pembroke Avenue Water Main Replacement. .


1,214.08


Pleasant Avenue Water Main Replacement and Ex- tension.


343.25


Prince Street Water Extension


492.69


Pumping Station Division:


Payroll


7,626.64


Fuel


9,553.98


Oil


151.62


Pumps. Boilers .


544.48


Cleaning Filter Beds


374.62


Care of Equipment, Grounds and Beds


236.34


Light.


139.41


Phone


222.10


Incidentals.


25.92


19,454.79


Sewer Division:


Filter Beds.


1,970.43


Repair and Care of Sewers


252.70


2,223.13


Rifle Range


146.92


City Survey


1,075.10


Sidewalk Curbing for Capron Park, Horton Field and South Attleboro School .


12.29


Equipment Repair


11.14


Improvement of Mechanic Street E. R. A.


368.10


Leroy Street Improvement .


50.00


Adamsdale Avenue Reconstruction .


325.99


North Main Street and Commonwealth Avenue


Widening


985.08


Emory and Pine Street Improvement.


109.35


1925-27 Street Widening Loan


483.53


North Avenue E. R. A. Drainage


87.97


West Street Construction ..


1,911.89


Ashton Road Construction


230.68


Curbing and Cement Walk Construction.


53.93


Pond Street E. R. A. Drain


61.12


579.68


194


ANNUAL REPORT


Improvement of Pond Street E. R. A ..


296.93


South Attleboro Rail Elimination and Replacement


868.93


Construction of Ruggles Street E. R. A.


150.00


Construction of Central Street E. R. A.


100.00


Hebronville Guard Fence.


85.08


East Fourth Street Improvement E. R. A.


555.30


North Main Street Construction E. R. A.


6,946.65


Construction of Bliss Avenue E. R. A.


176.90


County Street Drainage and Construction E. R. A. .


1,185.24


1935 South Main Street Hebronville Drainage E.R.A. .


1,186.15


South Main Street Improvement.


7,408.26


Dexter Street Construction.


2,141.89


South Avenue Reconstruction.


9,713.44


Tanager Road Construction .


751.12


County Street Pavement Construction.


13,925.97


Fisher Street Construction .


424.51


Public Works Highways (Third to Olive Street)


4,052.00


Public Works Highways (Olive to Thirteenth Street)


2,777.61


Fenton Avenue Construction .


1,101.95


W. P. A. Sidewalks and Curbing Project


3,484.34


Brook Street Drain Project.


1,021.13


Pembroke Avenue Construction


817.64


$188,825.01


JURY LIST FOR ATTLEBORO-1936


1 NAME


RESIDENCE


OCCUPATION


PLACE OF OCCUPATION


Abbott, Frank C. Adams, Clifford J.


25 Bicknell St. 50 Holman St. 18 Thacher St. 975 So. Main St.


Jeweler


Attleboro


Merchant


Attleboro


Carpenter


Attleboro


Unemployed


Attleboro


Audette, William E.


213 Pine St.


Jeweler


Attleboro


Balser, Charles W.


181 Mendon Road 16 Angell St.


Jeweler


Attleboro


Barton, Harvey E., Jr.


5 Atwood St.


Laborer


Attleboro


Bears, William S.


161 Locust St.


Furniture shop


Attleboro


Beland, Arthur


22 Carpenter St.


Wire Drawer


Attleboro


Bellavance, Julian


178 Pine St.


Jeweler


Attleboro


Betts, Lucien P.


55 Collins St.


Clerk


Attleboro


Bibby, William


225 Mendon Road


Mill hand


Attleboro


Blackburn, William A.


197 So. Main St.


Jeweler


Attleboro


Blackinton, Virgi.


388 So. Main St.


Editor


Providence


Blanchard, Albert T.


156 Cumberland Ave.


Salesman


Attleboro


Boivin, Albert


11 Parker St. 9-A Oak St.


Office Asst.


Attleboro


Bowman, Orie


33 Emory St.


Jeweler


Attleboro


Branaghan, George W.


29-B Pleasant St.


Jeweler


Attleboro


Bregnard, Alfred W.


59 East St.


Stamper


Attleboro


Brennan, Russell E.


11 East St.


Student


Boston


Brennan, William M.


52 Tiffany St.


Salesman


Attleboro


Briggs, Arthur M.


384 So. Main St.


Foreman


Attleboro


Broadbent, John E.


20 Ashton Road


Jeweler


Attleboro


Brousseau, Ovila S.


52 Orange St.


Clerk


Attleboro


Brown, George N.


55 Emory St.


Optical worker


Attleboro


Bruce, Isaac H.


351 So. Main St.


Merchant


Attleboro


Burt, Frank E.


175 South Ave.


Jeweler


Attleboro


Bussiere, George E.


82 Carpenter St.


Insurance Agent


Attleboro


Callahan, Robert E.


16 Foley St.


Public Works


Attleboro


Campbell, Ralph W.


125 Deanville Road


Auto Laundry


Attleboro


196


ANNUAL REPORT


Jeweler


Attleboro


Bolesky, John D.


Milk dealer


Attleboro


Barrett, William P.


Akerley, Clive H. Atwell, Russell


Carpenter, Earl B. Carpenter, Edwin H. Carroll, John B. Casey, John J.


35 Elizabeth St.


Jeweler


Attleboro


40} Elizabeth St.


Foreman


Attleboro


Printer


Attleboro


20 Elizabeth St.


Jeweler


Attleboro


Charlebois, Ulderic


24 Carpenter St.


Manager


Attleboro


Clarke, Howard R.


8 Maple St.


Jeweler


Attleboro


Clarke, James A.


17 Foley St.


Spinner


Attleboro


Cleary, Richard L.


14-A Leroy St.


Jeweler


Attleboro


Conlan, James B.


14 Horton St.


Die Cutter


Attleboro


Conro, Wray


24 Dean St.


Clerk


Attleboro


Cooney, J. Raymond


12 Benefit St.


Physical Director


Attleboro


Cornell, Fred H.


385 So. Main St.


Foreman


Attleboro


Cotton, Maurice W.


408 Washington St.


Steel worker


Attleboro


Cotton, William A.


41 Holman St.


Butcher


Attleboro


Cronin, William F.


9 Foley St.


Jeweler


Attleboro


Croteau, Albert C.


248 So. Main St.


Jeweler


Attleboro


Crowley, James H.


64 Orange St.


Truck Driver


Attleboro


DeLage, William N


19 Capron St.


Toolmaker


Attleboro


Delaney, Lyons F. H.


205 Highland Ave.


Manager


Attleboro


Dennis, Edward F.


94 Hope St.


Unemployed


Attleboro


Derosier, Dona


100 Dunham St.


Caretaker


Attleboro


Dion, Arthur N.


33 Pearl St.


Jeweler


Attleboro


Dion, Jean B.


30 Major St.


Jeweler


Attleboro


Dobra, Frederick


38 Elizabeth St.


Jeweler


Attleboro


Doherty, Lawrence A.


41 Pleasant St.


Jeweler


Attleboro


Doucette, George


50 Carpenter St.


Manager


Attleboro


Doyle, Edward N.


36 Horton St.


Jeweler


Attleboro


Duffy, Patrick J.


47} Emory St.


Shipping Clerk


Attleboro


117 So. Main St.


Teacher (resigned)


Attleboro


Eastwood, William F. Eaton, Arthur L.




Need help finding more records? Try our genealogical records directory which has more than 1 million sources to help you more easily locate the available records.