MANAGER'S REPORT
To Municipal Light Board, Town of Braintree, Mass.
Gentlemen :- I herewith submit my report of the busi- ness of this department for the twelve months ending De- cember thirty first, 1921.
1 We can again report considerable increase in the volume of business over the preceeding year, yet on the whole it was not entirely up to expectation, and this was due largely to the results of a disasterous fire early in the year which deprived the department of one of its largest customers, this corpora- tion was again connected to our service lines in November.
On March seven, 1921 we transfered all.outgoing service lines to the new switchboard located in that part of the building that was extended toward the street during the preceeding year, and we now have a modern board and switching apparatus capable of supplying service require- ments upward of five thousand kilowatts. This switch- board installation called for an outgoing service tower, which we had erected in the rear of the station and equipped with all modern transmission accessories.
April first we began the installation of two, two hundred sixty horse power rating Union water tube boilers, this work entailed the removal from the building of three old horizontal tubular boilers with uptakes, the construction of proper foundations for the new units, and the substitution of steel roof supports in place of the former wood trusses. July eleventh found this work completed to the extent of allowing us to put one of the boiler units under pressure and operate our own service supply.
These units were constructed to carry two hundred pounds steam pressure and are equipped with superheaters for one hundred degrees, all valves and fittings in pipe lines are constructed of steel with the necessary specifications for high pressure superheated operation.
Two new feed water pumps and one national feedwater heater with capacity for an additional six hundred horse power of boiler rating have been installed, and blank con- nections on present steam heater for future boiler and turbine additions have been provided.
Boilers are fired with fuel oil, three burners being standard equipment for each unit, and we have no difficulty in generating steam in one boiler "using two burners only" sufficient to maintain a steady load of six hundred and fifty kilowatts on turbine. Under proper load conditions we have proven by test that we can produce at switchboard four kilowatts per each gal of fuel oil consumed, and during the coming year we will without doubt obtain excellent results in fuel economy.
148
-
The old boilers that we were obliged to remove are stored near railroad sidetracks, and can be loaded on cars without any difficulty and at slight expense, they have been painted and otherwise properly protected from the elements, but we have not as yet been successful in procuring a pur- chaser.
The one hundred and fifty horse power Rollins engine has not been removed from foundation, while the one hundred and forty kilowatt generator was shipped to the Karl Andren Co., Boston, who are endeavoring to procure a purchaser.
We are again having some difficulty in procuring sufficient condensing water during extreme low tide periods, especially so when there is ice in the river, and it is my opinion that it will be necessary during the coming year to dredge our supply basin, and construct a new supply tank at a relatively lower level to the channel.
Our system of meter reading and collecting as recom- mended and adopted by the board in 1918 has proven both successful and efficient as evidenced by the fact, that during the present year we have not been obliged to write off to profit and loss one single bad account. This surely is most encouraging and convincing in comparison with the results obtained prior to the adoption of the present methods.
Two hundred and thirty-four new services were con- nected during the year making atotal of 2482 on file. Of this amount approximately thirty-five services are inactive.
These connections called for extension of lines on Liberty, Walnut, Arthur and Academy Streets, Harrison, Ellsworth and Lakeview Avenues, Wilmarth and Wyman Roads. Using 16 new 35 foot poles. 7,500 ft., No. 6 wire, and 1,500 ft. No. 2 wire. Other house connections required in process of installation 12,670 ft. No. 6 and 500 ft. No. 4 wire.
Replacement of poles were as follows: 13-35 Foot on Liberty Street, 3-35 Washington, 1-35 River, 1-35 Bowditch, 2-35 Elliot, 3-35 Union, 2-35 School, 2-35 Howard, 1-35 Cedar Road, 6-35 Cochato, 1-35 Brookside, 2-35 Elmwood Park, 1-40 Ft. Hollis Ave., 1-40 Franklin, 1-40 So. Braintree Square, 1-50 Ft. Mill Lane, making a total of forty-one poles.
Street lights were installed as follows: In East Brain- tree, 2-Thayer Street, 1-Sterling St. and 1-Commercial St., In So. Braintree, 1-Plymouth and Arbutus Avenue and 1-Lakeview Ave. requiring in process of installation 4,000 ft. No. 6 wire, costing in other stock and labor $275.00.
The total number of street lights now connected is 764.
149
1
The street lights were operated on 347 nights totaling 3065 hours and 45 minutes, consuming 157,580 kilowatt hours. Kilowatts generated at Station . 1,698,010 912,255
Kilowatts purchased
2,610,265
Distributed thus:
Consumers for light .
554,992
Consumers for power
1,531, 323
Street Lighting
157,580
Weymouth Light & Power
152,280
Station Consumption (Est.) . .
12,000
Line Loss
202,090
2,610,265
MANNUFACTURING ACCOUNT
Consumers' Lighting account .
$56,761.96
Consumers' Power account
48,888.68
Street Lighting account . 6,822.00
$112,472.64
MANNUFACTURING COSTS
Repairs Steam Plant
$2,228.27
Fuel Account
28,622.03
Station Tools .
127.60
Repairs Electric Plant
391.59
Automobile Account
3.645.97
Inc. Street Lamps
1.280.96
Distribution Tools .
1.68
Office Fur. & Fixtures
116.85
Repairs Real Estate
275.32
Repairs Lines
8,523.38
Oil & Waste
204.16
General Salaries
6,232.00
Station Wages
8,092.67
Distribution Wages .
2,517.60
General Office Expense
720.33
Water Account .
360.21
Insurance Account
1,401.36
Power Purchased
28.413.53
Repairs Meters
214.95
State Commission Tax
33.52
Manufacturing Balance
93,403.98 $19,068.66
150
PROFIT AND LOSS ACCOUNT
Cr.
By Balance December 31, 1920. $54,085.94
By Operating Balance Dec. 31, 1921. 19,068.66 Sundry Accounts (Lamps & Material) 826.37
By Interest Account
69.93
$74,050.90
Dr.
To Loans Repayment Account. .
6,212.96
To Dept. Sundry Plant Accounts
5,624.00
To Manf. Discts.
(Light and Power)
595.46
$12,432.42
Balance December 31, 1921
$61,618.48
OFFICE CASH ACCOUNT
To Balance at Office December
31, 1920.
$345.07
Consumers' Lighting Acc't :.
55,188.79
Consumers' Power Acc't ..
45,818.23
Street Lighting
6,832.00
Lamp Sales
1,446.85
Material Sales
2,342.37
Jobbing Wages .
429.47
Sale of Used Car (Saxon) ..
75.00
Sale of Automobile Supplies and Gasoline 67.51
Sales Misc. Junk
200.00
By Paid Otis B. Oakman, Treas.
$112,745.29 $112,745.29
TREASURER'S CASH ACCOUNT
To Balance Dec 31, 1920. $1,369.11
Cash from Plant Office 112,745.29
Interest on Dep. Cash Dep. 39.98
Interest on Operating Cash Deposits . 29.95
$114,184.33
By Paid Orders Drawn by
Municipal Light Board $113,683.62
Int. Paid to Dep. Fund Acc't. 39.98
$113,723.60
Balance December 31, 1921
$460.73
151
DEPRECIATION CASH ACCOUNT
Dr
To Balance December 31, 1920 . $4,982.84
Cash Trans. by Treas for 1921, 4,313.82
Interest Paid by Treas. 39.98
$9,336.64
Cr.
By Orders Paid to Steam Plant Account 1921 $8,798.28
Balance December 31, 1921 . $538.36
APPROPRIATION DEPRECIATION FUND 1922
To be paid from earnings of plant and computed thus: Total Cost of Plant Dec. 31, 1921 :
Real Estate $15,132.74
Steam Plant.
39,243.22
Electric Plant
27,496.18
Electric Lines
44,927.36
Transformers
13,048.87
Meters .
26,369.21
Street Lamps and Fixtures. 4,926.31
Less Land Value .
$171,143.89 1,065.00
$170,078.89
Dep. Fund for 1922 equals Three per cent $170,078.89 . . 5,102.36
APPROPRIATION STREET LIGHTING 1922
764 Lights .. $9.00 each
$6,876.00
To be expended thus: Payment to Dep. Fund .. .. $5,102.36
Payment to Constr. Acc .... 1,773.64
$6,876.00
BALANCE DECEMBER 31, 1921
Assets:
Electric Plant
$31,618.59
Steam Plant
54,176.18
Real Estate .
11,980.80
Transformers
16,130.46
Meter Account
22,503.42
Electric Lines
42,693.09
Inc. Street Lines & Fixtures
3,805.88
Inc. Series Lamps .
151.70
Consumers' Light Acc't.
4,414.72
152
Consumers' Power Account
6,693.09
Bills Receivable.
705.14
Town Treasurer Cash
460.73
Dep. Fund Cash .
538.36
Repairs Real Estate (Inv.).
8.40
Consumers' Lamps (Inv.) . .
834.56
Consumers' Supplies (Inv.) .
847.59
Distribution Tools and Appliances (Inv.) 909.37
Repair Lines (Inv.)
3,729.47
Station Tools (Inv.)
869.85
Oil & Waste (Inv.)
285.45
Repairs Steam Plant (Inv.)
1,154.63
Fuel Account(Inv.).
970.44
Automobile Acc't. (Inv.) ...
2,342.87
Electric Plant Repairs(Inv.)
835.80
Office Fur. & Fix. (Inv.).
912.75
$209,573.34
Liabilities:
Bills Payable .
$18,786.12
Appropriations for Const'n.
46,168.74
Loans Repayment Account.
83,000.00
Profit & Loss Acc't.
61,618.48
$209,573.34
AUDITORS REPORT
We have examined the accounts of F. B. Lawrence, manager of the Braintree Electric Light Department, to- gether with all inventories, and compared same with stock and appliances on hand, and approve them as rendered. Cash received and paid Town Treas. $112,745.29
Stock on hand as per "inventory"
13,855.88
Bills Receivable:
Light
$4,414.72
Power
6,693.09 705.14
Material
$11,812.95
Bills Payable $18,786.12 RALPH W. ARNOLD, PAUL MONAGHAN, Auditors, 1921.
153
Report of the Planning Board
Under the provisions of G. L. Chapter 41, Section 70, the Town of Braintree was required in 1921 to choose a Planning Board and did so at the last Annual Town Election.
The Board in the first year of its existence, found itself without funds and handicapped by its inexperience. Its function is purely advisory and is not to be confounded, as is often the case, with that of a board of survey.
Throughout the year several meetings were held and various minor matters were investigated, among them the extension of the State Highway from the Braintree line along Willard Street, West Quincy to Furnace Brook Park- way, and the question of the location of the dry dock near the Quincy boundary at Hayward's Creek. It has been found from examination of the doings of such boards in other towns that matters are often referred to them which under our practice go to various special committes. For example, in Waterown the problem of school housing and of a proposed civic center at Watertown Square appear this year, to have been referred to the Planning Board of that town.
This Board recommends that the Town investigate the advisability of accepting the provisions of the General Laws for the establishment of a board of survey and that pending action thereon, the Town instruct its various de- partments not to install utilities on unaccepted streets, un- less plans of such streets or proposed streets have been approved by the Planning Board.
Respectfully submitted,
CHARLES O. MILLER, Chairman. JONATHAN W. FRENCH, Secretary. MERTON L. EMERSON
154
REPORT OF THE FIRE DEPARTMENT
To the Honorable Board of Selectmen:
Gentlemen: I respectfully submit to you the annual report of the Fire Department for the fiscal year ending December 31st, 1921.
The following Board of Engineers were appointed for the year:
J. Samuel Hill
Frank O. Whitmarsh
Fred A. Tenney
George H. Holbrook Edward Avery Benjamin H. Woodsum
The Board met and organized as follows:
Fred A. Tenney, CHIEF Edward Avery, CLERK
There were 160 calls during the year, divided as follows: Box Alarms 45; Still alarms 115; Building fires 45; Automobile fires 5; woods and grass 83; dumps 12; bridges 5; false alarms 10.
Valuations of buildings $142,150.00
Damage to buildings
18,650.00
Insurance on buildings
105,900.00.
Insurance paid on buildings
18,425.40
Valuation of contents
93,900.00
Damage to contents .
8,319.01
Insurance on contents. 82,300.00
Insurance paid on contents 8,088.11
During the year there were two blanket insurance policies,
February 12th :
Valuation was .
$346,500.00
Insurance was .
354,081.45
Damage was. 336,091.45
Insurance paid
336,091.45
November Ist:
Valuation was
1,700,000.00
Insurance was
1,700,000.00
Damage .
2,146.00
Insurance paid.
2,146.00
PERMITS GRANTED
To set fires in open air. 241
To use dynamite . 24
Garage and gasolene permits 63
155
There were 23 permits granted the Massachusetts Oil Company to receive and deliver oil in the Harbor. The Gulf Refining Company to deliver oil to the Old Colony Gas Company - 2.
To sell fireworks between June 10th and July 10th . 8
Total amount of hose used during the year
21,050 feet
Total amount of chemical used
1,714 gallons 764
Total number of feet of ladder used .
RECOMMENDATIONS 1922
Salary Chief
$2,000.00
Deputy Chiefs
100.00
Permanent men (4)
6,060.00
Qualey's truck and driver
1,300.00
Call men .
1,800.00
Poll taxes
260.00
Extra pay of firemen
1,100.00
General expenses
6,856.00
Chief's car
1,300.00
New Hose .
1,000.00
Repairs on Fire Stations .
600.00
Motor driven ladder truck
8,000.00
Forest fires
1,000.00
Respectfull submitted, F. A. TENNEY, CHIEF.
156
ANNUAL REPORT
OF THE
WATER DEPARTMENT
OF THE
TOWN OF BRAINTREE
FOR
Year ending Decenber 31, 1921
Printed by Order of the Town
B
T
IMOI
..
MA
1640.
TS
SSA
H. W. BAILEY & COMPANY SO. BRAINTREE, MASS.
.1922.
ORGANIZATION
-
Report of Water Commisioners for the Year 1921
HON. JAMES T. STEVENS, Chairman WILLIAM C. HARRISON GEORGE A. WALKER OTIS B. OAKMAN, Treasurer W. L. GAGE, Secretary and Purchasing Agt. JOHN W. MULCAHY, Superintendent FRANCIS J. O'ROURKE, Chief Engineer
158
WATER COMMISSIONERS REPORT
The Board of Water Commissioners herewith submits the Annual Report for the year expiring December 31, 1921 as required by Article 2 Section 2 of the Town By-Laws:
The year just expired has been more favorable for progressing with additions and improvements that have long been delayed owing to excessive cost of everything connected with Water Works construction, and quite an amount of work has been accomplished which adds materi- ally to the efficiency of the System. At the Annual Town Meeting held in March last, the Board asked for authority to make several additions to the Main Pipes and were granted authority to proceed and specified amounts were placed at their disposal.
Under Article 49 of the Warrant, it was voted to re- appropriate $4,800.00 unexpended from the previous year for the extension of the mains on West Street to Five Cor- ners and the main on Storrs Avenue to connect with Elm Street to be taken from the revenue of Department. This work has been completed at a cost of $2,412.55 for West Street and $1,803.60 for Storrs Avenue, leaving a balance of the appropriation of $583.85 unexpended.
Under Article 51, it was voted to appropriate from the revenue of the Department $1,200.00 for the extension of the 6" main on Cedar Street to connect with the main on Elm Street. The extension has been completed at a cost of $1,296.57.
Under Article 52, it was voted to appropriate from the revenue of the Department $900.00 for extending the Main on Shaw Street and we have completed this extension at a cost of $816.26.
Under Article 54, it was voted to appropriate $1000.00 to complete a summer service on Grove Street from Plain Street to the residence of Mrs. T. F. Quimby. This extension was made at a cost of $999.94.
Under Article 56, it was voted to appropriate from the revenue of the Department $3,400.00 to extend the main on Plain Street from Liberty Street to the Nelson property on Plain Street. The extension has been completed at a cost of $3,344.58.
In addition to the above mentioned extensions provided for by vote of the Town, we have made additional exten- sions and connections as follows:
Under the river at Shaw St., bridge to re-
place a former pipe which had been
condemned costing $531.51
159
Extension of the 12" main on Tremont St.,
to Hobart Avenue, cost . 685.43
Harrison Avenue from Middle Street 6" main Cost. . 409.20
Lakeview Ave. 6" Main, cost 599.78
Wyman Road extension of 4" main, cost 633.78
Cresent Avenue 4" Main to take place of 1"
pipe, cost. 140.93
Renewal of 1" pipe on Thayer St., with
4" Main connecting with Cedar Cliff Road Costing . 909.79
Under Article 53, the Town voted to appropriate $4000 to be expended under the direction of the Water Commis- sioners for the development of an additional water supply, two thousand to be taken from the tax levy and $2,000.00 from the revenue of the Water . Department. Little pro- gress has as yet beenmade in the investigation contemplated owing to unfavorable weather conditions and non-comple- tion of the survey.
In July the $150,000.00 Water Loan of 1891 matured and was paid off and in October the last serial note of $1500. issued for the improvement of the Plant at the Great Pond Station was paid, and the outstanding funded indebtedness of the Water Department has been reduced to the Water Loan of 1896 of $6,000.00 maturing August 1, 1926. The value of the Sinking Fund to care for this loan is at this date $5,292.06 and we recommend that a sufficient amount be taken from the balance of the Water Department as of December 31, 1921 to liquidate the Loan and clear the Department from debt.
Notwithstanding these additions to the system which have been made the past year, the Commissioners feel that there are still further additions that are equally important to insure to the citizens a continuous supply of water and to add to the better protection of property from fire, the importance of which has been demonstrated by the rapid increase of population and the very marked increase in Real Estate. This increased demand for water has not been met with a corresponding increase in the facilities for producing it, and to secure adequate service for domestic and commercial uses and for additional fire protection, we make the following recommendations as the first and most important.
Another direct supply to the Stand-Pipe which can be had by completing the 6"line on Granite Street making a direct connection with the Stand-Pipe by King Hill Road, Granite Street to Five Cornersand WestStreet to Stand-Pipe.
160
In case of trouble in either supply pipe requiring shutting off of the water, there would still be direct connection with the Stand-Pipe and no inconvenience to consumers would ensue.
Continuation of the 12 inch main on Tremont Street from present 12 inch pipe to Academy Street eliminating two dead ends and increasing the pressure in this locality which under present conditions is not up to requirements.
Extensions through French Avenue from Union Street to Pearl Street to eliminate the dead ends on Union Street and Holbrook Avenue and give additional fire protection to extensive manufacturing interests in this vicinity which at present is entirely inadequate.
The extension of the 6 inch main on Washington Street from Cedar Street to Fairfield Street thereby eliminating two dead ends and giving a much needed relief to the in- habitants of Washington Park and vicinity. -
These recommendations are in line with the policy of the Board to discontinue wherever possible dead ends which are not only a source of annoyance to the consumer but an item of considerable expense to the Department as frequent calls are made to flush them which consumes much time of employees.
The Commissioners were much gratified by the con- fidence placed in their judgment at the Annual Meeting in March last as evidenced by the readiness with which they were granted their requests for authority to carry out their recommendations and trust the work that has been com- pleted the past year justifies that confidence.
The reports of the Secretary, Registrar, Treasurer, Superintendent, and Chief Engineer are hereto appended.
JAMES T. STEVENS, WILLIAM C. HARRISON, GEORGE A. WALKER, Water Commissioners of the Town of Braintree.
161
MAINTENANCE
R. E. Whitman $.20
G. E. Warren . .
.84
Braintree Auto Express
1.35
Thomas Groom & Co.
2.37
Diamond Union Stamp Co.
2.00
W. A. Torrey & Co.
7.02
The American City
4.00
Robert Porter
4.05
Norfolk County Registry
5.00
T. E. Burke & Co.
10.00
Library Bureau .
8.76
L. E. Muran & Company
18.13
W. L. Gage.
17:70
South Braintree Post Office.
182.48
H. W. Bailey & Co.
30.75
Observer Publishing Company
112.25
N.E. Tel. & Tel. Company
202.12
A. C. Trojano
40.92
Pinel Tool Company
30.00
Randolph Water Company
1,231.23
Fred O. Stevens . .
1,600.00
James T. Stevens .
100.00
William C. Harrison
100.00
George A. Walker
100.00
William L. Gage .
1,500.00
Pay of Men as per payroll .
1,685.85
$6,997,02:
GREAT POND STATION
Geo. E. Fogg .
$1.12
Pinel Tool Company
1.25
Dow Mfg. Company
. 1.25
Dyer & Sullivan .
1.32
Ashton Valve Company .
6.88
F. L. Chandler .
8.92
Waldo Bros. & Bond Co. 11.20
A. A. Drollett . 12.00
Rhines Lumber Company .
13.91
A. W. Chesterton Company
27.50
Braintree Auto Express . :
29.35
J. W. Meliconda . 31.10
G. E. Warren .
32.20
Walworth Mfg. Company
32.10
Underhay Oil Company .
38.83
Eagle Oil & Supply Company
47.00
·
162
Commonwealth Oil Company 184.20
Garlock Packing Company .
86.22
Hayes Pump & M'chy. Co.
89.55
Braintree Electric Light Dept.
138.10
H. S. Tarbox
344.18
N. Y. N. H. & H. R. R. Co.
340.68
Curran & Burton, Inc ..
1,593.19
J. F. Sheppard & Sons, Inc.
2,784. 58
Pay of Men as per payroll
5,458. 18
-$11,314.81
LITTLE POND STATION
R. W. Haskell
$1.00
1
P. S. Lynch .
1.50
Walworth Mfg. Company
2.25
Braintree Auto Express .
2.25
Dyer & Sullivan . .
3.32
Waldo Bros. & Bond Company
6.09
F. L. Chandler
6.46
R. A. Gage.
8.75
Braintree Electric Light Dept.
14.75
J. H. Mitchell . 15.00
Mass. Oil Refining Company
15.27
Woodsum Coal Company .
29.25
Pittsburg Plate Glass Company
38.13
J. F. Sheppard & Sons, Inc.
186.42
Pay of Men as per payroll .
494.37
$824.81
SERVICE WORK OUTSIDE STREET LINES
Woodsum Coal Company
$.96
Pinel Tool Company .
5.00
P. S. Lynch . 6.50
N. Y. N. H. & H. R. R. Co.
6.28
Chapman Valve Company .
5.81
F. L. Chandler
9.75
Walworth Mfg. Company
7.98
Alfred Lind .
11.25
Sumner & Dunbar.
30.00
Braintree Auto Express .
44.95
A. C. Harvey Company
95.75
A. W. Chesterton Company
102.52
"T. J. O'Brien .
21.00
W. H. Gallison Company .
182.12
Chadwick Boston Lead Co.
642.40
H. Mueller Mfg. Company
329.65
A. C. Trojano .
218.85
Pay of Men as per payroll
1,737.97
$3,458,74
· 163
..
SERVICE WORK IN STREET
F. L. Chandler $.75
Alfred Lind .
1.75
S. A. Neal, Agt.
2.72
Woodsum Coal Company
.72
Pinel Tool Company .
4.50
N. Y. N. H. & H. R. R. Co.
13.21
Braintree Auto Express
32.25
Frank Plumba 24.50
R. J. Teasdale 10.50
A. W. Chesterton Company
11.95
A. C. Harvey Company . 58.18
W. H. Gallison Company
42.43
· Sumner & Dunbar .
152.39
Weymouth Water Works .
25.20
H. Mueller Mfg. Company
191.16
Chadwick Boston Lead Co A. C. Trojano
101.95
Pay of Men as per payroll .
1,087.31
$2,185.33
SERVICE REPAIRS IN STREETS
F. L. Chandler
$1.80
Chadwick Boston Lead Co.
20.00
H. Mueller Mfg. Company
36.10
Woodsum Coal Company .
1.44
Pay of Men as per payroll
435.83
$495.17
RENEWAL SERVICE WORK IN STREET
Chadwick Boston Lead Company
$42.43
A. C. Trojano . 46.00
Pay of Men as per payroll
115.37
$203.80
HYDRANTS
Rensselaer Valve Company
$569.70
R. A. Gage
8.50
Pay of Men as per payroll
.
67.10
$645.30
HYDRANT REPAIRS
S. A. Neal, Agent $.51
Coffin Valve Company
1.60
A. C. Trojano .
6.20
Pinel Tool Company .
21.00
Pay of Men as per payroll
108.00
$137.31
164
423.86
FLUSHING AND TESTING HYDRANTS Pay of Men as per payroll $349.48
$349.48
METERS
National Meter Company
$317.20
John F. Diauto .
40.00
S. A. Neal, Agent
8.69
$365.89
METER REPAIRS
Braintree Auto Express .
$3.65
National Meter Company
327.88
Pay of Men as per payroll .
545.78
$877.31
READING, INSPECTION AND TESTING METERS
G. E. Warren & Co.
$9.92
H. W. Bailey & Co ..
11.75
Pay of Men as per payroll ... 965.56
$987.23
TOOLS
Pinel Tool Company
$47.80
A. W. Chesterton Company .
33.67
Walworth Mfg. Company
50.69
Braintree Auto Express .
7.45
Coffin Valve Company .
6.75
N. Y. N. H. & H. R. R. Co.
1.90
L. Pizzello .
4.50
Mrs. W. E. Maybury.
10.00
Braman, Dow & Company
.
6.72
H. Mueller Mfg. Company
36.11
Dow Mfg. Company .
1.25
Mrs. C. H. Custance
1.50
W. H. Cobb
32.85
J. Nicol, Jr.
25.92
F. L. Chandler
.75
Franklin Rubber Company
31.50
R. Belyea .
1.05
Chandler & Farquhar
1.38
T. J. O'Brien .
3.40
Waldo Bros. & Bond Company
31.75
Dyer & Sullivan . .
.33
Commonwealth Oil Company
6.00
Pay of Men as per payroll
63.00
.
$406.27
165
MAIN PIPE EXTENSIONS
G. E. Warren
$.40
A. McGlone
12.00
S. A. Neal, Agent . .82
Braintree Auto Express
5.75
N. Y. N. H. & H. R. R. Co.
15.00
C. R. Bestick
16.00
Geo. E. Fogg 20.00
R. Allen Gage
277.60
Mass. Oil Refining Company 98.35
Rhines Lumber Company . 30.63
J. F. Shepard & Sons, Inc. . 3.00
Chapman Valve Mfg. Company
7.00
A. W. Chesterton Company . .
28.37
Waldo Bros. & Bond Company
Need help finding more records? Try our genealogical records directory which has more than 1 million sources to help you more easily locate the available records.