Pennsylvania lines west of Pittsburgh : a history of the flood of March, 1913, Part 8

Author: Garrett, Charles Wilbur, 1876-
Publication date: 1913
Publisher: [Pittsburgh, Pa. : Press of Wm. G. Johnston & Co.]
Number of Pages: 322


USA > Pennsylvania > Allegheny County > Pittsburgh > Pennsylvania lines west of Pittsburgh : a history of the flood of March, 1913 > Part 8


Note: The text from this book was generated using artificial intelligence so there may be some errors. The full pages can be found on Archive.org (link on the Part 1 page).


Part 1 | Part 2 | Part 3 | Part 4 | Part 5 | Part 6 | Part 7 | Part 8 | Part 9 | Part 10 | Part 11 | Part 12 | Part 13


3-26


3-26


400


60


Embankment washed out west of Bridge No. 39 and Bridge No. 40 under No. 2 track.


3-27


1000


Mingo Junction, Ohio.


45


3000


Land slide covering No. 1 and No. 3 tracks and a few cubic yards on No. 2 track. No. 2 track opened immediately . . . .


3-27


4-4


3000 (Exeava.)


300


Tuscarawas, Ohio.


94


3600


Roadbed washed out 125' long, 4' to 8' deep. Nine pile bents placed under No. 2 track, Romigs Crossing ...


3-28


3-30


1200


150


120


96


1900


Ballast washed out under both tracks, 750' long, 2' to 4' deep. .


3-29


3-30


750


900


Gnadenhutten, Ohio.


97


1300


Bridge No. 92, north end west abutment undermined. Filled with riprap. (Dis- covered April 3) ...


4-3


700


West pier undermined at north end but not discovered at time.


Lock 17, Ohio.


3-29


3-29


50


100


97 99


5000 00


Roadbed washed out 100' long, 2' to 3' deep Embankment washed out 20' long on south side of tracks up to end of ties. .


3-29


40


99


4100


Roadbed washed out 300' long, 4' deep, No. 2 track bloeked up and both tracks filled .. Roadbed washed out, 600' long, 2' to 8' deep ..


3-29


4-2


2000


720


3-30


4-2


1000


360


100 101


3800 00


Roadbed washed out, 300' long, 2' to 8' deep Embankment on north side of tracks washed out to end of ties, 20' long ..


3-30


4-2


50


101


2800


Roadbed washed out, 3000' long; 5-bent trestle built under No. 2 track at small culvert.


3-30


4-2


1000


3600


60


Port Washington.


102


2200


Roadbed washed out 750' long, 2' to 7' deep; 40" concrete pipe put in temporarily under all three tracks; ballast badly washed for 500' east .. .


3-30


4-2


4000


900


102


4400


Roadbed washed out 400' long, 3' deep; ballast washed 200' further ...


3-30


4-3


1500


1000


103


200


Ballast washed out under all tracks 3000' long; including 1 hole 400' long, 3' deep; 1 hole 60' long, 4' deep, and 1 hole 150' long, 2' to 8' deep.


3-30 3-30


4-3


2000


1500


103 104


00


No. 1 track washed out 40' long, 3' deep .. . . Roadbed washed out 1600' long, 2' to 5' deep; ballast washed out 300' farther on east end.


3-30


4-3


4000 100


2300 360


104


1300


Ballast washed out 300' long ..


3-30


4-4


Cu. Yds. of Fill


Cu. Yds. of Ballast


2nd


35


3217


Wing wall washed out at Bridge No. 34 .. Ballast washed out under three tracks in Collier Yard, 200' long.


Date Cleared


Lineal Feet Trestle


122


3-29


4-2


800


540


100


2400


3300


50


PITTSBURGH DIVISION. DETAILED LIST OF DAMAGE DONE BY FLOOD OF MARCH, 1913.


Date Cleared


Lineal Feet Trestle


from


+Ft.


LOCATION AND DESCRIPTION


1st Track


2nd Track


1st Track


2nd Track


104


2000


Roadbed washed out 250' long, 12' to 15' deep. Trestle built on No. 2 track. Ballast washed badly for 1800' west .. .. .


3-31


4-4


4000


1000


132


104


4300


Embankment 300' long, 12' to 15' deep, washed away along No. 2 track .. .


3-31


4-4


1000


106


00


Ballast washed out 4300' long, including 1 hole 750' long, 2' deep, and 1 hole 850' long, 2' deep.


3-31


4-4


1000


2500


New Comerstown.


108


2300


Roadbed washed out under thrce tracks, 50' long, 2' to 3' deep. .


3-31


4-12


300


100


109


4800


Roadbed washed out 860' long, 14' deep, both tracks ..


4-3


4-12


43000


1000


803


480


110 110


3600


Ballast washed out 1350' under 3 tracks, including 1 hole 400' long, 3' to 15' deep .. . 4-3


4-4


4500


1600


Isleta.


112 112


800


Roadbed washed out 50' long, 2' deep


4-3


4-4


60


112


1700


Roadbed washed out 450' long, 2' to 6' dcep


4-3


4-4


2400


540


112


2900


Roadbed washed out 600' long, 2' to 8' deep


4-3


4-4


3000


700


117 118


2200 00


Bridge No. 96. Embankment badly washed Embankment washed along south sodline 2700' long, and 20' of Morgans Run East- ward platform washed away.


4-3


1000


120


00


Light slip on south slope along No. 4 track.


4-3


50


120


1500


Light slip on south slope along No. 4 track.


4-3


50


120


4200


North embankment washed under No. 3 track 50' long, 6' dcep


4-3


200


120


4600


North embankment washed out to end of ties along No. 3 track 100' long.


4-3


300


121


2500


Series of small holes washed out under No. 4 track


4-3


3500


100


123


100


North embankment washed out under No. 1 track, 500' long, 2' to 6' deep. . . .


4-3


4-13


600


150


123


700


North embankment washed out under No. 1 track, 160' long, 2' deep


4-3


4-13


100


30


123


3000


1500' of roadbed along No. 2 track badly washed to end of ties. . .


4-3


4-13


1000


100


123


4600


1600' of embankment washed out under drill track and 500' of siding to J. Clow & Sons plant all washed away.


4-3


4-13


6000


1300


124


700


Roadbed washed out under three tracks, 1000' long, 4' to 16' deep, and tracks washed out of line 20'.


4-3


4-13


22000


1800


124


2400


Roadbed washed out 450' long, 6' to 8' deep. Six cars derailed from siding. Ballast and bank cut out to end of ties 800' long, 4' deep, along No. 1 track, east of hole . . Roadbed washed out 1200' long, 6' to 10' deep. 1300' ballast washed out east of hole. 4 cars overturned.


4-3


4-13


4500


1000


124


4200


4-3


4-13


19000


3000


126


2600


Roadbed washed out 2700' long, 10' to 25' deep ..


4-12


4-20


60000


3300


2106


(Low Grade)


2140 396


800


Ballast out under No. 2 track 500'.


4-3


200


1000


Roadbed washed out 120' long, 2' deep.


4-3


4-4


150


West LaFayette.


4-3


200


Morgans Run.


(Excava.)


(Excava.)


Coshocton.


Cu. Yds. of Fill


Cu. Yds. of Ballast


Mile Post


Pittsburgh


123


PITTSBURGH DIVISION. DETAILED LIST OF DAMAGE DONE BY FLOOD OF MARCH, 1913.


Mile Post from Pittsburgh


+Ft.


LOCATION AND DESCRIPTION


1st Track


2nd Track


1st Track


2nd Track


127


00


Bridge No. 100, double track through truss; Piers Nos. 2 and 3 washed out; Span No. 2 settled at west end. Spans 3 and 4 turned over into river bed. After No. 2 track was opened on pile trestle Spans 3 and 4 were renewed for 2 tracks with deck plate girders on cluster pile bents.


4-13


6-11


306


. .. .


Tyndall.


127


4700


Bridge No. 101, concrete rail-top under- grade, and embankment 100' long for three tracks, washed out. Pile trestle built for three tracks, 85 lin. ft. each.


4-3


4-13


1600


180


85


85


Conesville.


131


00


Embankment along No. 2 track badly washed 1100' long


1400


Adams Mills.


133


00


4-3


3000


300


133


2700


North embankment badly washed 2250' long. No. 1 track washed out 500' long, 4' deep. . No. 1 track and siding to Icehouse washed out, 300' long. Ballast washed out 1800' long. .


4-3


200


1000


134


00


No. 1 track washed out 2' to 6' deep, 7100' long.


4-3


10000


2000


134


4200


Bridge No. 104, 10' arch, washed out; embankment washed out under both tracks, 400' long, 10' to 25' deep.


4-3


4-12


15000


500


344


300


Trinway.


136


00


1500' yard track washed out in Trinway yard ..


136


1300


Embankment slipped out under No. 1 and No. 4 tracks, 100' long; 23 piles driven along south side of bank ...


4-2


4-2


100


137


2700


Embankment badly washed along north side for 250'.


4-2


4-2


500


Frazeysburg.


144


300


Bridge No. 113, both abutments under- mined, cracked and settled; tracks shifted north and concrete slabs blocked up on timber .. .


4-2


4-2


Total Main Line.


230,500 3100 (Excava.)


36,760


4,386


2,971


New Cumberland Branch


4-4


3500


2000


6000 lin. ft. track lined and surfaced. 8000 lin. ft. sunken track surfaced. 35000 lin. ft. track mud cleaned off.


800 (Excava.)


P. W. & K. R. R.


3-31


6000


600


1200 lin. ft. track lined and surfaced. 13000 lin. ft. sunken track surfaced. 30000 lin. ft. track mud cleaned off.


Hickory Branch


3-31


500


Total, Branches.


10,000 800


2,600


(Excava.)


Date Cleared


Cu. Yds. of Fill


Cu. Yds. of Ballast


Lineal Feet Trestle


900


124


Gnadenhutten, Ohio.


April 21, 1913.


Bridge 92, over Tuscarawas River. West approach fill washed out, and replaced with stone and riprap. Abutment slightly cracked.


Port Washington, Ohio.


April 21, 1913.


View east, showing track as replaced for regular service.


125


Coshocton, Ohio, west of.


April 22, 1913.


View east, east of Bridge 100, showing new fill replacing conditions shown in the frontispiece.


-


Coshocton, Ohio, west of.


April 22, 1913.


View east, east of Bridge 100, showing pile trestle over deepest washout in fill.


126


Coshocton, Ohio, west of.


April 22, 1913.


Bridge 100, over Muskingum River; second span raised and supported on timber falsework on account of undermining of pier.


Coshocton, Ohio, west of.


April 22, 1913.


Bridge 100, over Muskingum River; trestle replacing one track across channel of river completed; driver starting work for second track.


127


Coshocton, Ohio, west of.


April 22, 1913.


Trestle replacing Bridge 101, a cattle pass. Rail used in cribbing is part of the top of the old bridge, which had a slab top of rail, brick and concrete.


Trinway, Ohio, east of.


April 22, 1913.


Trestle replacing Bridge 104, carrying an overflow from the Ohio Canal; 10 foot stone arch washed out.


128


CHAPTER 19. COLUMBUS TERMINAL DISTRICT. INDIANAPOLIS AND CINCINNATI DIVISIONS.


As all the damage in the Columbus Terminal district was done at one stroke, and as most of the repairs were made by the Indianapolis Division on both divisions, it seems desirable to let one account cover the whole situation.


The Scioto River flows eastwardly for about two miles toward Columbus, then turns abruptly south, separating Columbus into two parts, the main City on the east bank, and a residential section on the west side, which for convenience will be called West Columbus. Just before making the turn to the south, the Scioto River is joined by the Olentangy. These streams occupy a low valley, and as every flood stage would inundate West Columbus, that section has been protected by levees where the fill of the Big Four Railway does not answer that purpose. Through this district the rail- ways have all been raised in recent years to separate the grades of streets and railways. All tracks have been carried on embankments and overhead bridges span the principal streets.


The river, in this instance, was called upon to carry about twice as much water as the waterways at the bridges would accommodate, and the result was that the levees were overrun within a short time. Their construction was not calculated to resist the erosion from overflow, and these levees gave way very promptly. The fill of the Cincinnati Division then acted as a dam, with openings at each of the street bridges. These were insufficient to pass the great quantity of water, and the force of the deluge cut the embankment away wherever there was an opening until a sufficient waterway was provided. At the street crossings the current was so strong that it tore up the street surface and the concrete substructure and excavated holes ten or twelve feet deep. The material of the destroyed fill was washed far away; even the heavy boulders which made up a large part of the gravel used for fill were carried hundreds of yards, and strewn over everything, sometimes even piling up in the houses several feet deep.


The flood carried many buildings from above down through this district, and tore up and carried away innumerable residences through the whole of West Columbus. Houses were tumbled topsy-turvy everywhere; some were even left standing on their roofs; some were cut in two-one part being swept away, the other standing. Pianos, furniture and debris were scattered over the whole landscape when the water went down.


There were four main washouts on the Cincinnati Division tracks:


One between the Scioto River Bridge and the Hocking Valley crossing.


One just west of the Hocking Valley crossing.


One at the B. & O. S. W. crossing.


One at Central Avenue, including the viaduct,


Several others occurred in the same district, but they were not serious.


129


4


1


-


Bridge NÂș3 (Indpls)and) over Scioto River


-Two miles West


-


Grandwien


Goodat 1


Ballast washed out


Pccasth Ry


-


Sales


mbankment washed out.


Ballast washed


out


Ballast washed out


--


--


-


H.V. RY


MalA)


-


Dublin


Pine


Olentangy


NORINHA@


PLCESTL.RY


scioto


Breaks in Levee


CCC & StL Ry Embankment forms


avec


River


28


AT&OC.RR


Breaks in Levez


Tracks und


mely


East abutment totally destroye Nest abutment domaged.


TYCH


Graad


Columbus, Ohio, West Side.


Sketch map showing tracks of Indianapolis and Cincinnati Divisions, direction of currents over lowlands, and points of main damage to roadbed and bridges.


130


nbortment


entirely go


*Kment gone


--


ccc&.StERy


West Columbus, Ohio.


March 26, 1913.


Cincinnati Division tracks, looking west from T. & O. C. crossing. Sandusky street


bridge over Scioto River appears in distance at right.


Marble Cliff, Ohio.


April 1, 1913.


Alignment of Bridge 3, over Scioto River, after west pier was undermined.


131


The Indianapolis Division tracks across the lowland north of the river were badly washed on both sides of the Olentangy River bridge (No. 1, Indianapolis Division). The bridge itself was not damaged, as it was protected by a heavy riveted-truss bridge of the Hocking Valley just above it set at an angle with the current, deflecting the debris which otherwise would probably have swept away Bridge 1. At Cincinnati Division Bridge 3, over the Scioto, the water came to the bottom of the lower chord, and a gang of men constantly kept the drift pushed down so as to pass under the steel work and it was not damaged. Bridge 3 on the Indianapolis Division, some three miles up stream, was but slightly damaged at first, although one pier had been under- mined sufficiently to throw the bridge slightly out of line, so that it was deemed unsafe for passenger trains. For one or two days days, however, it was used in hauling filling material for repair work, until it was further undermined and rendered unfit for any use on the 28th.


The water did not go down enough to permit repair work to commence until the 27th. On the 28th the Indianapolis Division had one track restored to service through from Columbus over the Olentangy and Scioto Rivers and the valley ibetween, but the Scioto River bridge (No. 3) was put out of service late in the day, after having been used but a few hours for relief trains for Dayton, and local passenger trains.


Bridge 3 is a double track, deck truss bridge, of three spans, high above the stream. The west pier was undermined on the north (upstream) side so that one of the two supports of the superstructure was let down enough to move the top of the truss 23 inches to the north, settling vertically 9 inches. The south end of the pier remaining in place, a crack developed in the pier, about 12 inches wide, from the top to the bottom of the masonry.


On the 29th, the pier was tied together with timbers and steel rods and the crack closed about an inch. Small dump cars were then used to dump stone around this pier (and the other one as well, as a precautionary measure) and support afforded the stone work. Sufficient rip-rap was put in the stream to form a foundation for frame bents to support the north half of the superstructure, which was jacked into place. It was not until April 7th that it was reopened for one track. Further repair was turned over to a contractor, the bridge being supported so that the old pier might be torn down and replaced with one of concrete. The track on the damaged side of the bridge was restored to service May 27th at reduced speed.


Work on the Cincinnati Division washouts commenced on March 27th. On the 28th the washout west of Hocking Valley crossing was made ready for work train service, and on the 29th, the one east of the crossing. A track was thus provided by which work trains might reach the more extensive break at the B. & O. S. W. crossing. There a "rundown" was made on either side, and the track connected across the gap on the 30th, eribbing being used where the water was still running through. The track was gradually raised and the crib filled in with stone from nearby quarries and dirt from a steam shovel put to work at Grandview.


At the fourth washout, Central Avenue viaduct, stringers were placed between the damaged abutments, supported on cribbing, and a fill made, using material from a contractor's steam shovel cut in near Alton. One track was put in service here on April 1st, and double track service was re-established on the Cincinnati Division on April 2d except for four gauntlets where the breaks had been, where only one track had been replaced. It was not until the 16th that the last of these gauntlets had been removed.


132


Within a few weeks, work was started on a new bridge to replace Central Avenue viaduct, necessitating a run-around track for temporary use.


At the Sandusky Street viaduct, the roadway under the bridge was partially filled with debris, but the structure was not damaged. At Rogers Avenue, the south wing walls were undermined by the deep scouring, and were repaired by filling in with con- crete, the structure being otherwise undamaged.


133


Marble Cliff, Ohio.


April 1, 1913.


Bridge No. 3, over Scioto River, showing west pier undermined on north side; cracked pier held together with iron rod bands; Rip-rap thrown in stream around it, and walkway from shore to pier suspended by ropes from Bridge superstructure.


Marble Cliff, Ohio.


April 23, 1913.


View west, at Bridge 3, over Scioto River, showing west pier being replaced.


134


West Columbus, Ohio.


March 31, 1913.


Looking east over washout west of Hocking Valley Crossing.


4+1


West Columbus, Ohio.


March 31, 1913.


Sandusky Street viaduct, looking toward river channel, at point where levee was washed entirely away, taking large water main with it.


135


CHICAGO. MILWAUKEE


30075


TLONTIC COANT DENTATEE


PUGET SOUNDI


203'


West Columbus, Ohio.


April 23, 1913.


Sandusky Street subway, looking north, after roadway had been cleared.


HAIRLA SIONTITI


West Columbus, Ohio.


March 31, 1913.


Rodgers Avenue viaduct-viaduct itself not damaged, but roadbed badly washed and pavement under viaduct destroyed.


136


SY


West Columbus, Ohio.


April 23, 1913.


Rodgers Avenue viaduct, showing condition of street pavement and subgrade under viaduct. Foundations of viaduct being deepened.


West Columbus, Ohio.


March 31, 1913.


B. & O. Crossing, looking west, showing forces at work replacing roadbed destroyed.


137


West Columbus, Ohio.


March 31, 1913.


View east, at B. & O. Crossing. Replacing fill washed away. Cars standing on old fill to right of center of picture, in distance.


West Columbus, Ohio.


April 6, 1913.


B. & O. Crossing; one track sufficiently restored to permit passage of trains.


138


West Columbus, Ohio.


April 23, 1913.


B. & O. Crossing, looking west; ballasting new track for resumption of service at regular speed.


West Columbus, Ohio.


March 30, 1913.


View east, showing Central Avenue viaduct being replaced with cribbed trestle, preparatory to making temporary fill.


139


West Columbus, Ohio.


March 31, 1913.


Looking north on Central Avenue; filling in from temporary cribbed trestle where viaduct was washed away.


West Columbus, Ohio.


April 6, 1913.


Central Avenue viaduct; fill temporarily replacing bridge.


140


CHAPTER 20. INDIANAPOLIS DIVISION.


The Indianapolis Division runs at right angles to the drainage basins, and the damage sustained was to bridges over the streams it crosses. The portion of the divi- sion from Urbana west to Richmond lies but a short distance south of the main divide, and as it lies also in the belt of heaviest rainfall, it was here that the flood first affected the Pennsylvania Lines.


At Piqua the Miami River, and near Richmond the East Fork of the White River, came up to the track level early on the 24th of March, and by night all the streams were at unprecedented flood stages. The track was badly washed out at New Madison, Ohio, and during the night a work train was started from Bradford Junction to make repairs. They had gone but about seven miles when Bridge No. 58, a stone arch over Middle Creek, or "Dry" Creek, near Gettysburg, Ohio, went down with the rear of the train, the heavy engine and three cars having crossed in safety. The foreman and five laborers were drowned; 14 other laborers, the conductor and two brakemen were injured. The injured were taken to Greenville and cared for until a detour route could be found to get them to a hospital at Piqua.


At about the same time, on account of washouts west of Urbana, train No. 3, enroute to Chicago, was detoured north over the Big Four Railway, to be taken to Union City and there returned to the Pan Handle. As it pulled over the Mad River bridge at West Liberty, the same stream which had caused the trouble west of Urbana, the bridge went down with the engine and one car. The train having been reversed in delivering it to the Big Four, the engine was backing, and the car next to it was the Columbus-Chicago sleeper. The engineman, fireman and pilot were on the engine. The first two got ashore with but slight injuries. The pilot was washed down the river but was able to cling to a bridge about half a mile down stream, from which he was rescued after daybreak. One end of the sleeper rested on the bank, and the other end swung around until the car rested on its side along the river bank. Several passengers were slightly injured, and a brakeman, who was riding in the end of the car next the engine, was killed or drowned and his body was not recovered for several days.


The injured were provided with blankets from the Pullman cars, and food supplies were confiscated from the express car for the passengers, for the track had been washed out back of the train, so that it was impossible to reach it from either side. It was not until noon (March 25th), when a relief train succeeded in getting within a mile and a half of No. 3, that the passengers, including the injured, could be transferred to this train and brought back to Urbana. Part of the crew was left in charge of the train, until it was returned to Urbana on the afternoon of the 28th.


On the 25th, the Indianapolis Division, cut into many pieces, found on its hands six passenger trains marooned at outlying points, with twelve more at Columbus terminal, and two at Richmond; and fourteen freight trains marooned at outlying points. Three


141


of these passenger trains (all east bound) were at Bradford Junction, where the Railway Y. M. C. A. afforded facilities for caring for passengers. Some of the passengers amused themselves by getting up a newspaper, which a local publisher printed for them, on March 27th. Two trains, one in either direction, were stopped at New Madison, and one westbound train at Urbana.


The damage sustained by the Indianapolis Division, outside of Columbus ter- minal, which has been mentioned in a previous chapter, consisted of damage to bridges as follows:


Bridge No. 35, west of Urbana, over large ditch.


Both new and old line bridges undermined at one end. The old line bridge had to be supported temporarily on piling.


Bridge 37, west of Urbana, over large ditch.


Both new and old line bridges undermined.


Bridge No. 39, west of Urbana, over Spring Creek.


Both new and old line bridges undermined.


East abutment of bridge, carrying eastward track, so undermined that piling was necessary to carry it temporarily.


Bridge No. 50, Piqua, Ohio, over Miami River and Canal.


The bridge itself was not damaged, although the west abutment was undermined and one span had to be partly supported on piling. The east approach to the bridge was entirely washed away, and 140 lineal feet of pile trestle had to be con- structed before the gap could be closed.


Adjacent to this bridge were the concrete piers for a new bridge to replace it, being built in connection with track elevation work through Piqua. These new piers were not damaged, but the contractor's outfit engaged in the work was badly wrecked by the flood.


Bridge No. 58, west of Gettysburg, over Middle Creek.


Stone arch bridge, 18 foot span, completely destroyed.


Temporarily replaced with cribbing and frame bents. Will be replaced with 30 foot arch.


Bridge No. 64, west of Weavers, over Mud Creek.


West abutment undermined. Bridge supported temporarily on timber bents. Bridge No. 92, west of New Paris, over East Fork White River.


Abutments and pier practically destroyed. Superstructure for one track in river, had to be replaced with pile trestle; superstructure for second track supported on timber bents. Bridge to be replaced with through truss bridge with thirty feet longer span.


The road bed was damaged in a great many places, but few of the washouts were serious and most of them were repaired by simply replacing the ballast.


On March 28th, repairs had advanced sufficiently that one track was open over the Division except at Bridge 3, Marble Cliff; Bridge 50, Piqua; Bridge 58, Gettysburg; and Bridge 92, New Paris.


On March 29th, one track was put in service over Bridge 92, and a foot bridge was gotten across the gap at Bridge 50. The passengers from the four eastbound trains at New Madison and Bradford were brought to Piqua, where they walked across Bridge 50 to another train; then to Marble Cliff, where they walked across Bridge 3, over the Scioto; and then to Columbus, arriving about midnight. Thence those for the


142


Q


--


Urbana, Ohio, west of.


April 2, 1913.


Bridge No. 37, on old line, approaches washed away, abutments undermined.


Urbana, Ohio, 314 miles west of.


April 2, 1913.


View east at Bridge 39, over Spring Creek, showing undermined abutment.


143


Piqua, Ohio.


April 2, 1913.


Showing fill at east approach to Bridge 50, over Miami River and Canal, replaced by temporary trestle.




Need help finding more records? Try our genealogical records directory which has more than 1 million sources to help you more easily locate the available records.